Year Completed: 2011
Location: Fridley, MN
Client: Cummins Corporation
Square Footage: 28,000 SF
Cummins Power Generation (CPG), now called Cummins Power Systems, is a global company whose operations both globally and regionally are overseen from the Fridley, Minnesota campus. Hagen Christensen & McIlwain Architects has completed the design of a 28,000 SF Hemi-anechoic Test Facility. It is the largest-in-the-world type of acoustic sound test facility of its kind. Test chambers in this facility are utilized to certify generator sets of all sizes developed and manufactured by CPG. This facility provides CPG with the ability to address zoning and code compliance for markets/regions throughout the world. This project provides CPG with an anchor to their Research and Development Center of Excellence. Construction was completed on this facility in September, 2011.