Significant progress has been made at Woodbury City Hall. During a site visit last Thursday we were able to observe various stages of construction throughout building. One of the main design features the entire project, the front desk / lobby redesign is finally starting to take shape with the installation of the Kasota Limestone at the front desk and service counter.
Millwork and countertops currently being installed along with the laminated glazing assembly that matches the existing color of the curtainwalls is really starting to give an overall view of the final product.
Various offices, New & Existing are in the process of receiving paint, carpet, and glazing. .
While the Millwork in the Break room have been completed.